East Holly Street Project Update

asphalt-3431322_1920

There is a lot of activity on East Holly Street this week, so additional closures have been put in place for safety. The first closure runs from Central Ave to 3rd Ave. The second closure is from 4th Ave through 9th Ave. The intersections at 3rd and 4th Avenues will remain open.

 

 

Truck Traffic:  Truck traffic will detour to Central Ave and 14th St SE. Signage will guide truck traffic along the detour. A detour map can be found on the project website: www.mdt.mt.gov/pubinvolve/eastholly. For truck traffic heading to Sidney Sugars, special signage has been put in place to direct traffic along the detour to Sidney Sugars.

 

Non-Truck Traffic:  A detour route will not be established for non-truck traffic during the 2-block closures of East Holly Street. Motorists should utilize alternative streets during closures.

 

If you would like direct updates on East Holly construction,

  • text “eastholly” to 555888, or
  • email eastholly@kljeng.com, or
  • call the construction hotline at 1-800-987-3681